TIMELINE STAGE
26th September 2014 Phase 1 and 2 planning application submitted to Northampton Council
23rd October 2014 Presentation to Northampton Alive by Redefine International P.L.C.
27th October 2014 Dedicated Microsite hosting information and plans on the redevelopment project go live
29th Oct – 02nd Nov 2014 Public consultation exhibition held at Weston Favell Shopping Centre
March 2015 Phase 1 and 2 works commences
September 2015 Completion of phase 1 and 2 works